PROJECT DATE: ONGOING
LOCATION : Zonguldak
INDUSTRY : IRON AND STEEL

As the main contractor, Supply, Manufacturing, Construction and Assembly Works within the Scope of the 2nd Blast Furnace Project. Demolition and rebuilding of one of Erdemir's current 2nd blast furnace.

Fabrication and erection of 20,000 tons of steel up to 120mm thickness; 260.000 dia-inch pipes manufacturing and erection; 475 piles up to 55 meters depth; 30,000 m3 of concrete works; new sinter silo ERECTION; Lifting operations up to 750 tons; electrical and instrumentation works, insulation, sandblasting and painting operations; pre-commissioning operations and commissioning of the plant.

Scope of Services

Bored Pile works (475 pieces-16.800 meters)